Australia’s $7.3 billion infantry fighting vehicle program is carrying what auditors have described as “very high technical risks” due to issues identified in the Department of Defence’s procurement and evaluation processes.
The Australian National Audit Office (ANAO) found that Land 400 Phase 3 – one of the largest capability acquisition projects in the history of the Army, delivering 129 Hanwha Redback vehicles – has evolved into a more uncertain and technically exposed program than originally intended.
The audit was conducted to provide Parliament with independent assurance on whether Defence tender processes and contracting arrangements have been effective in supporting value for money and in delivering the intended capability.
According to the findings, while the tender process broadly adhered to governance requirements, the audit highlighted a series of compounding risks, many of which were embedded early and remain unresolved.
At the centre of the concern is Defence’s decision to move away from its stated requirement for a mature and proven solution. Instead, the department pursued what the ANAO describes as a “more developmental pathway”, increasing exposure to integration, schedule and technical risks.
This shift has had cascading effects, it said, leaving the project grappling with technical uncertainty in core capability areas.
As of early 2026, the ANAO identified very high technical risks specifically tied to mobility and lethality – two of the most fundamental attributes of an infantry fighting vehicle.
These risks stem from the integration of systems and components not yet proven in a vehicle of this class, combined with Defence-imposed design requirements that added complexity.
Schedule pressure has further amplified this, with the program accelerated following the 2023 Defence Strategic Review, compressing the timeframe available for testing, validation and remediation.
According to the audit, this has reduced Defence’s margin to identify and resolve issues before key delivery milestones, increasing the likelihood that problems will emerge later in the lifecycle when they are more costly and harder to fix.
The ANAO’s findings suggest these risks were not fully or consistently reflected in the decision-making process.
In particular, the audit states that the implications of the more developmental approach were not clearly communicated to the government, nor consistently reflected in tender evaluation and contracting decisions.
The ANAO discovered inconsistencies in how risk adjustments were applied, which it suggests weakened value-for-money assessments.
Additional indicators reinforce the program’s fragile risk posture, including missed mitigation steps and the waiving of some contractual requirements. The audit also stated Defence overstated progress through remediation actions and failed to make timely payments to the contractor, resulting in $483,929.39 in penalty interest.
Overall, the audit points to high risk, uncertainty and a reduced margin for success, with challenges in delivering fully capable vehicles within the planned timeframe. It included two recommendations: strengthening advice to government and improving the timeliness of supplier payments.
While Defence maintains that the selected platform offers the best capability and value for money, it has acknowledged the findings in the Auditor General’s report and has agreed to both recommendations.
“Following a rigorous tender evaluation process, the Hanwha Redback Infantry Fighting Vehicle was selected,” said Defence in its response.
“In 2023, following the Defence Strategic Review, the project was accelerated to deliver the vehicles two years ahead of the original schedule. This required a risk-based delivery approach in partnership with Australian industry.
“The acquisition strategy articulated an open approach to market. Military-Off-The-Shelf options were not the agreed acquisition strategy, nor Defence policy at the time.
“Defence acknowledges the ‘very high’ risks identified in the report and notes that these risks are subject to mitigation action by the project.
“The preferred tenderer offered the best capability to meet Defence’s requirements and the best value for money.”