Contract risk in focus as Snowy 2.0 target climbs to $22.2 billion

Snowy Hydro has raised the target cost of its Snowy 2.0 pumped hydro project to $22.2 billion, with a higher-cost scenario of $25 billion. Full commissioning is now targeted for late 2029.

The company announced the figures on 22 October, after its principal contractor, Future Generation Joint Venture (FGJV), completed a comprehensive cost reassessment.

The new target is $10.2 billion above the $12 billion estimate announced at the project’s August 2023 reset, when commercial operation of all units was targeted for December 2028.

Snowy Hydro attributed the increase to immature design at the final investment decision, contractor productivity shortfalls, underestimated delivery scope and equipment, and services and labour costs that exceeded the 2023 allowances. 

The higher-cost scenario reflects the project’s uniqueness, risk and technical complexity, as well as FGJV’s cost-estimating challenges.

The announcement follows an Australian National Audit Office (ANAO) report, published on 18 June 2026, which found Snowy Hydro had been only partly effective in managing delivery. 

It identified weaknesses in contractor accountability, risk management and the quality of monitoring data.

The 2023 reset replaced the fixed-price engineering, procurement and construction contract with a hybrid incentivised target-cost arrangement that included reimbursable elements. 

The ANAO found this shifted cost risk to Snowy Hydro, with the Commonwealth, as owner, carrying most of the exposure.

The revised contract shares savings and overruns on target-cost work but caps FGJV’s liability for overruns. 

The ANAO also found that the incentive framework was not working as intended.

Snowy Hydro said the $22.2 billion target cost should not be equated with an equivalent taxpayer funding requirement.

At the previous $12 billion estimate, around $4 billion was Commonwealth equity, with the remainder financed through government and bank loans and the company’s own cash flows. Funding arrangements for the revised cost are still being developed.

Snowy Hydro CEO Dennis Barnes defended the move away from fixed pricing.

“I have no doubt that moving from a fixed price contract, which was never suitable for such scale, uniqueness and complexity, has protected the project from an even greater cost increase,” he said.

“It’s also likely that under a fixed price contract, the project would again be stopped under the weight of billions of dollars of claims from the contractor, as it was prior to the reset.”

Barnes also argued that Snowy 2.0’s long-term value to Australia’s energy reliability is stronger than ever.

“The scale of Snowy 2.0’s energy storage is world-leading. More than half of the total energy storage the grid needs by 2050 will come from Snowy 2.0 alone.”

Snowy Hydro said FGJV now has an operational project control office supported by enhanced data and analytics. 

Other measures include embedded independent delivery and cost specialists, a new board oversight committee with external megaproject advisers and changes to contractor leadership.

As at September 2026, machine tunnelling was 65 percent complete and power station complex excavation had reached 90 percent. Construction design was 96 percent complete, compared with 44 percent at the reset.

In its 23 October response, the federal government reaffirmed its commitment to completing the project, citing its contribution to energy security and the renewable energy transition. 

It said it would consider how best to support Snowy Hydro and apply additional project oversight, with further announcements to follow.

Snowy 2.0 highlights the importance of understanding who bears the risk when a contract changes, and whether they can manage it. 

Buyers accepting greater exposure to cost overruns need reliable forecasts, a clear view of contractor performance, incentives that work in practice, and the ability to intervene early when delivery falls short.